Tag Archives: Substantial Completion

Time

Tick Tock: Don’t Let the Statute of Repose or Limitations Time Periods Run on Your Construction Claims


This entry was posted by on .

In Wascher v. ABC Ins. Co., No. 2020AP1961, 2022 Wisc. App. LEXIS 110 (Feb. 9, 2022), the Court of Appeals of Wisconsin considered whether the plaintiffs were barred — by Wisconsin’s 10-year statute of repose for improvements to real property claims and the six-year statute of limitations for breach of contract claims — from bringing a lawsuit against the original builders of their home. The plaintiffs alleged negligence and breach of contract against the masonry subcontractors, asserting that they improperly installed the exterior stone cladding. The court found that the plaintiffs’ claims against the original builders were time-barred. Continue reading

This entry was posted in Construction Defects, Contracts, Statute of Limitations-Repose, Wisconsin and tagged , , , , , , .