Signing Agreement

What Did the Contract Say Again? Preventing Application of a Prime Contract Based Solely on Generic Incorporating Language in the Subcontract


This entry was posted by on .

In Edifice Constr. Co., Inc. v. Arrow Insulation, Inc., No. 79407-8-1, 2020 Wash App. LEXIS 359, the Court of Appeals of Washington considered whether subcontractors could be bound by the arbitration clause in a contract between an owner and a general contractor. In determining that the subcontractors were not bound by the arbitration clause in the prime contract, the court found that the general contractor failed to meet its burden of showing that the subcontractors were on notice of the specific terms of the prime contract. Continue reading