Category Archives: Statute of Repose

Gavel

Washington Court Finds that Statute of Repose Fraud Exception Argument Lacks Energy


This entry was posted by on .

Statutes of repose are generally meant to be absolutes, providing clarity to potential defendants such as contractors. However, in limited scenarios, some states have allowed for exceptions to the defense. For instance, fraud is one potential exception that has been recognized in several jurisdictions and is often raised by parties on the basis of public policy. In Puget Sound Energy, Inc. v. Pilchuck Contractors, Inc., No. 80162-7-1, 2020 Wash. App. LEXIS 2862 (unpublished), the Court of Appeals of Washington determined whether it would allow a fraud exception to its statute of repose for construction activity. The court upheld the trial court’s holding that the statute of repose barred the appellant’s claims, declining to entertain a fraud exception. Continue reading

This entry was posted in Construction Defects, Statute of Repose, Washington and tagged , , .
Time

In Massachusetts, the Statute of Repose Applies to Consumer Protection Claims Against Building Contractors


This entry was posted by on .

In Bridgwood v. A.J. Wood Construction, Inc., 105 N.E.3d 224 (Mass. 2018), the Supreme Court of Massachusetts determined that the statute of repose barred the plaintiff’s consumer protection claims commenced more than six years after the occurrence of the event that gave rise to the claims. In Bridgwood, the homeowner filed suit against the contractors who had performed renovations 15 years earlier. The homeowner asserted that concealed faulty electrical work caused a fire 11 years after the work was completed. The complaint alleged that the contractors, by violating Mass. Gen. Laws. Chapter 142A §17(10), committed an unfair and deceptive act pursuant to Mass. Gen. Laws Chapter 93A. Continue reading

This entry was posted in Massachusetts, Statute of Repose and tagged , .
Fire

Minnesota Clarifies the “Machinery/Equipment” Exception to the Statute of Repose for Improvements to Real Property and Adopts Test for Establishing a Post-Sale Duty to Warn


This entry was posted by on .

In a recent decision, Great Northern Ins. Co. v. Honeywell Int’l, Inc., 2018 Minn. LEXIS 236, the Supreme Court of Minnesota addressed two important legal questions: (1) did the “machinery and equipment” exception to Minnesota’s statute of repose for improvements to real property allow the plaintiff to bring claims against the manufacturer of a component part used in a home’s heat-recovery ventilator; and (2) did the defendant have a post-sale duty to warn the plaintiff? In answering the first question, the court clarified the meaning of the term “machinery” as used in Minnesota’s statute of repose. In answering the second question, the court adopted a test to apply to determine the circumstances under which a defendant in a product’s chain of distribution has a post-sale duty to warn. Continue reading

This entry was posted in Minnesota, Products Liability, Statute of Repose, Uncategorized and tagged , , .

Texas Court of Appeals Holds that Plaintiffs Bear the Burden of Proof as to the Willful Misconduct Exception to the Statute of Repose


This entry was posted by on .

In Brooks v. CalAtlantic Homes of Texas, Inc., 2017 Tex. App. Lexis 9466, the Court of Appeals of Texas considered whether a defendant moving for summary judgment on the grounds that the statute of repose expired also bears the burden of establishing the absence of applicable exceptions to the statute of repose. In Texas, a plaintiff alleging a construction defect in an improvement to real property must file a lawsuit within ten years of the date of substantial completion of the improvement. Continue reading

This entry was posted in Construction Defects, Statute of Repose, Texas and tagged , .

House Bill Clarifies Start Point for Florida’s Statute of Repose


This entry was posted by on .

The Florida legislature recently enacted a law clarifying when the ten-year statute of repose begins to run for cases involving “improvements to real property,” as that phrase is used in Florida Statute Section 95.11. House Bill 377 was signed into law on June 14, 2017 and took effect in all cases accruing on or after July 1, 2017. This amendment is significant to subrogation professionals evaluating when cases involving contractors and design professionals are time barred.

Continue reading

This entry was posted in Florida, Statute of Repose and tagged , , .

Applying the Statute of Repose for Construction Claims, Colorado’s Supreme Court Finds Third-Party Claims Timely-Filed


This entry was posted by on .

In Goodman v. Heritage Builders, Inc., 390 P.3d 398 (Colo. 2017) (en banc), the Supreme Court of Colorado clarified the parameters for timely-filing third-party claims for indemnification or contribution in construction defects cases. The court held that C.R.S. § 13-80-104(1)(b)(II) – addressing when a party can file third-party indemnification and contribution claims – controls over the two-year statute of limitations period set forth in C.R.S. § 13-80-102 and the six-year statute of repose period in C.R.S. § 13-80-104(1)(a). Thus, in Colorado, so long as third-party claims are brought during the litigation or within ninety days after the date of judgment or settlement, such claims should be timely.

In Goodman, Heritage Builders, Inc. (Heritage) acted as the general contractor for a home sold to Karen and Courtney Lord (collectively, the “Lords”). The county issued a certificate of occupancy for the home in September 2006. In November 2011, the Lords sold the home to Richard Goodman (Goodman), who discovered alleged construction defects in the home between March and June 2012.  In July of 2013, Goodman sent Heritage informal notice of his claims. He sent them a formal notice of claim – as required by Colorado’s Construction Defect Action Reform Act, C.R.S. §§ 13-20-801 to 31-20-808 – in October of 2013. Thereafter, Heritage sent a notice of claim letter to Studio B Architects (Studio B) and Bluegreen, Inc. (Bluegreen), alleging design deficiencies in the home. Subsequently, on December 20, 2013, Goodman filed suit against Heritage and some of its contractors and, in response, Heritage asserted cross-claims and filed a third-party complaint against Studio B and Bluegreen, among others. Arguing that Heritage’s third-party claim against it was barred by the six-year statute of repose contained in C.R.S. § 13-8-104(1)(a), Studio B moved for summary judgment. Bluegreen joined the motion. Finding that Heritage’s claims against Studio B and Bluegreen arose, at the earliest, when Heritage received informal notice of the alleged defects in July of 2013 – more than six years after the home’s date of substantial completion – the trial court held that the statute of repose barred Heritage’s third-party claims against Studio B and Bluegreen. The Supreme Court of Colorado disagreed.

As noted by the court on appeal, in general, construction defect claims are subject to the two-year statute of limitations in C.R.S. § 13-80-102 and the six-year statute of repose in C.R.S. § 13-80-104(1)(a). However, construction defect claims against other parties – “who may be liable to the claimant for all or part of the claimant’s liability to a third person” – are governed by C.R.S. § 13-80-104(1)(b)(II). Pursuant to this subparagraph, notwithstanding the provisions of § 13-80-104(1)(a), contribution and indemnification claims against third-parties may be brought in either: “(1) the construction defect litigation before a settlement or entry of judgment or (2) a separate lawsuit after a settlement or entry of judgment.” Giving the “notwithstanding” language its controlling effect, the court held that, although § 13-80-104(1)(a) incorporates the two-year statute of limitations in § 13-80-102 and contains a six-year statute of limitations for construction defect claims, § 13-80-104(1)(b)(II) is the statute section under which courts determine the timeliness of third-party contribution and indemnification claims. Pursuant to § 13-80-104(1)(b)(II), so long as third-party indemnification and contribution claims are brought during the construction defect litigation or within ninety days following the date of judgment, the claims are timely. Thus, because Heritage brought its third-party claims against Studio B and Bluegreen before any judgment or settlement, the court held that its claims were timely.

The analysis in Goodman serves as a reminder to subrogation professionals that, when deciding whether construction defect-related claims are timely, it is important to review the language of the applicable statute of repose. Where, as in Colorado, there is language in a subsection of the statute of repose indicating that the statute applies “notwithstanding” other statutory sections, subrogation professionals reviewing the statute should accord the subsection containing the “notwithstanding” language appropriate weight.

This entry was posted in Colorado, Statute of Repose and tagged , , , .

Colorado’s Court of Appeals Considers How the Statute of Repose Applies in Multi-Contractor Construction Cases


This entry was posted by on .

In Sierra Pacific Industries v. Bradbury, 2016 Colo. App. Lexis 1274, 2016 COA 132 (September 8, 2016), Sierra Pacific Industries, Inc. (Sierra Pacific), a subcontractor hired to supply windows and doors on a condominium construction project, filed an indemnification action against Jason Bradbury, d/b/a Bradbury Construction, Inc. (Bradbury), a sub-subcontractor Sierra Pacific hired to install windows and doors. After the trial court granted summary judgment in Bradbury’s favor, the Court of Appeals of Colorado addressed whether Colorado’s six-year statute of repose for construction defect claims, C.R.S. § 13-8-104, barred Sierra Pacific’s claims against Bradbury. In particular, the court addressed the question of whether the tolling period for indemnification claims set forth in § 13-8-104(b)(1) tolls the repose period. The court also addressed how the phrase “substantial completion” should be interpreted in multi-contractor construction cases. Finally, the court considered whether Sierra Pacific could rely on the “repair doctrine” to extend the “substantial completion” date, the date on which the statute of repose begins to run. Sierra Pacific reminds us that, when a defendant invokes a construction defect statute of repose to defeat a plaintiff’s claims, it is important to analyze how the jurisdiction at issue defines the phrase “substantial completion” and how it applies tolling arguments to the statute of repose.

Continue reading

This entry was posted in Colorado, Statute of Limitations - Tolling, Statute of Repose and tagged , , .